Setup reminders
LOGIQ C9 Series – Basic Service Manual 3-3
5482298-100 English Rev. 5
Setup reminders
Average setup time
• Unpacking the LOGIQ C9 Series: 30 minutes
• Set up LOGIQ C9 Series wo/options: 30 minutes
• DICOM Network Configuration: 30 minutes or more,
depending on the configuration
• Install Insite: 0.5 hour
The LOGIQ C9 Series installation and functional checkout will
take approximately 1 hour. LOGIQ C9 Series consoles with
optional equipment may take slightly longer.
Setup warnings
WHEN USING ANY TEST INSTRUMENT THAT IS CAPABLE
OF OPENING THE AC GROUND LINE (I.E., METER’S
GROUND SWITCH IS OPEN), DON’T TOUCH THE
ULTRASOUND SYSTEM!
To prevent electrical shock, connect the unit to a properly
grounded power outlet. DO NOT use a three to two prong
adapter. This defeats safety grounding.
DO NOT wear the ESD wrist strap when you work on live
circuits and more than 30 V peak is present.
DO NOT operate this unit unless all board covers and frame
panels are securely in place. System performance and cooling
require this.