EasyManuals Logo
Home>GE>Medical Equipment>Vivid E7

GE Vivid E7 User Manual

GE Vivid E7
736 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #63 background imageLoading...
Page #63 background image
GE
D
IRECTION GB091046, REVISION 2 VIVID E9 / VIVID E7 BT’13 SERVICE MANUAL
Chapter 1 - Introduction 1 - 25
Section 1-6
Lockout/Tagout (LOTO) requirements
Follow OSHA Lockout/Tagout requirements (USA) or local Lockout/Tagout requirements by ensuring
you are in total control of the AC power plug at all times during the service process.
To apply Lockout/Tagout (LOTO):
1.) Plan and prepare for shutdown.
2.) Shutdown the equipment.
3.) Isolate the equipment.
4.) Apply Lockout/Tagout Devices.
5.) Control all stored and residual energy.
6.) Verify isolation.
All potentially hazardous stored or residual energy is relieved.
WARNINGWARNING
ENERGY CONTROL AND POWER LOCKOUT FOR VIVID E9 / VIVID E7.
WHEN SERVICING PARTS OF THE SYSTEM WHERE THERE IS EXPOSURE TO
VOLTAGE GREATER THAN 30 VOLTS:
1. FOLLOW LOCK OUT/TAG OUT PROCEDURES.
2. TURN OFF THE BREAKER.
3. UNPLUG THE VIVID E9 / VIVID E7.
4. MAINTAIN CONTROL OF THE POWER PLUG.
5. WAIT FOR AT LEAST 20 SECONDS FOR CAPACITORS TO DISCHARGE, AS THERE ARE NO TEST POINTS TO
VERIFY ISOLATION. THE AMBER LIGHT ON THE OP PANEL ON/OFF BUTTON WILL TURN OFF.
BEWARE THAT THE MAIN POWER SUPPLY AND BACK END PROCESSOR MAY BE ENERGIZED EVEN IF THE POWER
IS TURNED OFF WHEN THE CORD IS STILL PLUGGED INTO THE AC OUTLET.
Signed
Date
TA G
&
LOCKOUT

Table of Contents

Other manuals for GE Vivid E7

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE Vivid E7 and is the answer not in the manual?

GE Vivid E7 Specifications

General IconGeneral
BrandGE
ModelVivid E7
CategoryMedical Equipment
LanguageEnglish

Related product manuals