IRECTION GB091046, REVISION 2 VIVID E9 / VIVID E7 BT’13 SERVICE MANUAL
10 - 6 Section 10-5 - System maintenance
Section 10-5
System maintenance
10-5-1 Preliminary checks
The preliminary checks take about 15 minutes to perform.
Refer to the VIVID E9 / VIVID E7 user documentation whenever necessary.
Table 10-2 System preliminary checks
Step Item Description
1.
Ask & Listen
Ask the customer if they have any problems or questions about the equipment.
2.
Power up
• Turn the VIVID E9 / VIVID E7 power on and verify that all fans and peripherals turn on.
• Watch the displays during power up to verify that no warning or error messages are displayed.
3.
Probes
Verify that the VIVID E9 / VIVID E7 properly recognizes all probes.
4.
Displays
Verify proper display on the monitor and touch panel.
5.
Presets
Backup all Customer Presets to an appropriate media.
6.
Image Archive
Back up the Image Archive onto appropriate media.