GE
D
IRECTION GB091046, REVISION 2 VIVID E9 / VIVID E7 BT’13 SERVICE MANUAL
8 - 282 Section 8-14 - Peripherals replacement
Section 8-14
Peripherals replacement
8-14-1 DVD R/W drive replacement
The VIVID E9 / VIVID E7 may be equipped with one or two DVD drives. If two drives are installed, one
is for storing data and one for recording the streaming video from the optional DVR board inside the
BEP. On units without the DVR option, a Drive Bay Storage Box is installed in the empty DVD drive
location.
8-14-1-1 Preparations
When preparing for the replacement, you must perform the following steps:
1.) Power down the VIVID E9 / VIVID E7.
2.) Disconnect the Mains Power Cable from the wall outlet.
3.) Disconnect all probes and external I/O cabling.
4.) Remove the Side Covers.
5.) Remove the Top Cover.
ENERGY CONTROL AND POWER LOCKOUT FOR VIVID E9 / VIVID E7.
WHEN SERVICING PARTS OF THE SYSTEM WHERE THERE IS EXPOSURE TO
VOLTAGE GREATER THAN 30 VOLTS:
1. FOLLOW LOCK OUT/TAG OUT PROCEDURES.
2. TURN OFF THE BREAKER.
3. UNPLUG THE VIVID E9 / VIVID E7.
4. MAINTAIN CONTROL OF THE POWER PLUG.
5. WAIT FOR AT LEAST 20 SECONDS FOR CAPACITORS TO DISCHARGE, AS THERE ARE NO TEST POINTS TO
VERIFY ISOLATION. THE AMBER LIGHT ON THE OP PANEL ON/OFF BUTTON WILL TURN OFF.
BEWARE THAT THE MAIN POWER SUPPLY AND BACK END PROCESSOR MAY BE ENERGIZED EVEN IF THE POWER
IS TURNED OFF WHEN THE CORD IS STILL PLUGGED INTO THE AC OUTLET.