96 - 1
Accumulator
Removal and Replacement
Removal
1 Park the machine on level ground, lower the loader
arms, switch off the engine and chock all four wheels.
Release all hydraulic pressure in the accumulator by
selecting the SRS ON and operating the loader arm
hydraulic lever.
! DANGER
Before disconnecting or dismantling the accumulator
discharge all gas pressure. Failure to comply can cause
rapid discharge of gas and/or hydraulic fluid which can
result in death, personal injury and damage to the
machine.
Hyd 2-5
2 Discharge the accumulator, refer to Service
Procedures, Smooth Ride System -
Charging/Discharging the Accumulator.
3 Disconnect hydraulic hose A and plug.
4 Loosen both ‘U’ clamps B and slide the accumulator
towards the front of the machine. When clear of the ‘U’
clamps carefully lower and withdraw accumulator.
Replacement
Replacement is a reverse of removal.
1 Charge the accumulator, refer to Service Procedures,
Smooth Ride System - Charging/Discharging the
Accumulator.
2 Operate the machines hydraulic system. Check for
correct operation and leaks.
3 Replenish the hydraulic system with the recommended
hydraulic fluid as required, refer to Section 3 Fluids,
Lubricants, Capacities and Specifications.
Section E Hydraulics
9803/3280
Section E
96 - 1
Issue 1
Smooth Ride System
S308290
A
B
B
www.WorkshopManuals.co.uk
Purchased from www.WorkshopManuals.co.uk

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the jcb 214e and is the answer not in the manual?

jcb 214e Specifications

General IconGeneral
Brandjcb
Model214e
CategoryOther
LanguageEnglish

Related product manuals