Generate a connecon between inverter and »EASY Starter«
For commissioning the inverter with the »EASY Starter«, a communicaon link with the inverter is required.
This can be established in a wired manner only.
How to establish a communicaon link via the X16 engineering port to the inverter:
Precondions
•
The inverter is ready for operaon (mains voltage is switched on).
•
No errors or faults.
Required accessories
•
Engineering PC with installed »EASY Starter«
•
Standard network cable
1. Insert the network cable into engineering port X16 of the inverter.
2. Use the network cable to connect the inverter to the PC on which »EASY Starter« is installed.
3. Open the »EASY Starter« Start.
The "Add devices" dialog is shown.
4. Select the "Ethernet" connecon.
5. Press the Insert buon.
The »EASY Starter« searches the selected communicaon path for connected devices. Following successful
connecon, the inverter is shown in the device list. The »EASY Starter« tabs then provide access to the
inverter parameters.
Commissioning
Precondions
•
The mechanic
al and electrical installaon of the inverter is complete.
•
If necessary, the motor is mechanically decoupled from the system.
•
Check whether the system can be mechanically damaged if the non-decoupled drive makes
uncontrolled movements.
•
The inverter is supplied with voltage.
•
For parameterizaon purposes, it makes sense to supply the device with 24 V if the mains voltage and
the motor data deviate from the default seng.
•
If it has been ensured that the mains voltage and motor data sengs correspond to the actual
condions, the mains voltage can be connected.
•
The connecon between the inverter and the engineering PC with installed »EASY Starter« has been
established.
•
The »EASY Starter« is open and connected to the inverter.
•
The device list of the »EASY Starter« contains the inverter with the correct device descripon.
•
For an explanaon of where the device list can be found, please consult the online help of
the »EASY Starter«. Press the F1 key to call up the online help.
•
No fault is indicated by the inverter diagnoscs.
•
Check the LED status displays. LED status display ^ 178
•
Check the error messages.
•
Check available applicaon credit on the storage medium.
Commissioning
Commissioning
176