EasyManuals Logo
Home>Siemens>Circuit breakers>8DA10 Series

Siemens 8DA10 Series User Manual

Siemens 8DA10 Series
214 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #105 background imageLoading...
Page #105 background image
861-9601.9 • INSTALLATION AND OPERATING INSTRUCTIONS • 8DA10 • Revision 11 105/214
Installation
23 Performing the power- frequency voltage test
If required, a test with rated short-duration power-frequency withstand voltage can be
performed at the readily installed switchgear on site. The busbar voltage transformers are
designed for a repeat test at 80% U
D
at 60 Hz according to IEC 62271-200.
Preparing the power-
frequency voltage test
Check the SF
6
gas filling (see page 60, "Checking the SF
6
gas pressure").
Before the test, remove non-disconnectable voltage transformers which are not suitable at
least for tests at 80% values according to IEC 62271-200.
Close the transformer bushings in a surge-proof way.
Switch the voltage transformer disconnector of the disconnectable voltage transformers to
OPEN position.
For the rated short-duration power-frequency withstand voltage test, first close the three-
position disconnector and then the circuit-breaker in the incoming panel.
Close all free sockets in the test section in a surge-proof way.
Earth and short-circuit all test sockets of the voltage detecting system.
Switch all other three-position disconnectors to READY-TO-EARTH position.
Apply the power-frequency test voltage in a surge-proof way at the cable connection
bushing via test adapters.
The rated short-duration power-frequency withstand voltage test can now be performed.
Performing the power-
frequency voltage test
Apply 80 % of the rated short-duration power-frequency withstand voltage consecutively to
phases L1, L2 and L3 for 60 seconds each.
WARNING
Hazardous electrical voltage!
An incorrectly performed high-voltage test can cause death, serious injury and property
damage.
Observe the specifications for prevention of accidents.
Observe the operating instructions and work instructions of the switchgear operator.
Have the high-voltage test only performed by operating personnel who was instructed in
theory and practice of switchgear operation (see page 10, "Qualified personnel").
Keep a minimum safety distance of 3 m during the test.
Install safety barriers.
Earth test leads when test is complete.
NOTICE
Considerable property damage
During the high-voltage test, connected non-disconnectable inductive voltage
transformers may be damaged.
During commissioning, perform the high-voltage test before installing the non-
disconnectable voltage transformers.
Remove already mounted non-disconnectable inductive voltage transformers.
Close the transformer bushings in a surge-proof way.
Check the SF6 gas filling (see page 60, "Checking the SF
6
gas pressure").
Switch the disconnecting facility for panels with disconnectable voltage transformers to
OPEN position before performing the high-voltage test.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens 8DA10 Series and is the answer not in the manual?

Siemens 8DA10 Series Specifications

General IconGeneral
BrandSiemens
Model8DA10 Series
CategoryCircuit breakers
LanguageEnglish

Related product manuals