POWER TRIM AND TILT 8-13
Brushes
Measure length of each brush.
\ 09900-20101 : Vernier calipers
Brush length :
Standard : 9.8 mm (0.39 in.)
Service limit : 5.5 mm (0.22 in.)
If measurement exceeds service limit, replaced brush.
O-ring
Inspect O-ring between PTT motor and PTT pump case for cuts,
nicks or tears.
PTT MOTOR ASSEMBLY
Assembly is reverse order of disassembly with special atten-
tion to the following steps.
1. Install armature to brush holder first.

When installing armature, exercise care to avoid break-
ing brushes.
2. Match up previously scribed alignment marks.
3. When assembling field case to brush holder, proceed by
pulling PTT motor cables out of field case.
4. Apply Silicone Seal to PTT motor cable holder and grom-
mets, then install cable holder screw.
M 99000-31120 : Suzuki Silicone Seal
5. Fix cable protector tube to PTT motor cables with heat-re-
sisting tape.
40 mm
(1.6 in)
Tape
M
O-ring
10 mm
(0.4 in)

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Suzuki DF140Z and is the answer not in the manual?

Suzuki DF140Z Specifications

General IconGeneral
BrandSuzuki
ModelDF140Z
CategoryOutboard Motor
LanguageEnglish

Related product manuals