CVHE-SVX02M-EN
11
NNoottee:: The chiller should remain within its protective
shrink-wrap covering during storage.
Type of Requirement
Trane Supplied
Trane Installed
Trane Supplied
Field Installed
Field Supplied
Field Installed
Foundation
• Meet foundation requirements
Rigging
• Safety chains
• Clevis connectors
• Lifting beam
Disassembly/Reassembly
(as required)
• Trane will perform or have
direct on-site supervision
of the disassembly and
reassembly work (contact
your local Trane office for
pricing)
Isolation
• Isolation pads or spring
isolators
• Isolation pads or spring isolators
• Optional spring isolators, when required, are
installed by others; do NOT overload springs and do
NOT install isolation springs if they block serviceable
parts such as the oil tank system, service valves,
etc.
Electrical
• Circuit breakers or fusible
disconnects (optional)
• Unit-mounted starter
(optional)
• Power factor correction
capacitors (PFCCs)
(optional)
• Jumper bars
• Temperature sensor
(optional outdoor air)
• Flow switches (may be
field supplied); for
installation instructions
for the ifm efector®
flow detection controller
and sensor, refer to
“Water Flow Detection
Controller and
Sensor,” p. 28 or Trane
literature that shipped
with the device
• Remote-mounted
starter (optional)
• Circuit breakers or fusible disconnects (optional)
• Electrical connections to unit-mounted starter
(optional)
• Electrical connections to remote-mounted starter
(optional)
• Wiring sizes per submittal and National Electric Code
(NEC)
• PFCCs (remote mounted starter optional only)
• Terminal lugs
• Ground connection(s)
• Jumper bars
• BAS wiring (optional)
• Inter-processor communication (IPC) wiring (AFD
and remote-mounted starters only)
• Control voltage wiring (AFD and remote-mounted
starters only)
• Oil pump interlock wiring (AFD and remote mounted
starters only)
• High condenser pressure interlock wiring (AFD and
remote-mounted starters only)
• Chilled water pump contactor and wiring including
interlock
• Condenser water pump contactor and wiring
including interlock
• Option relays and wiring
• Tracer® SC communication wiring (optional)
Water piping
• Flow sensing devices
(may be field supplied)
• Taps for flow sensing devices
• Taps for thermometers and gauges
• Thermometers
• Strainers (as required)
• Water flow pressure gauges
• Isolation and balancing valves in water piping
• Vents and drain on waterbox valves (one each per
pass)
• Pressure relief valves (for waterboxes as required)
PPrree--IInnssttaallllaattiioonn