Checking the installation
115
Checking the installation
What this chapter contains
This chapter contains checklists according to which the assembly of converter
modules into a cabinet is inspected at ABB factory.
Visual inspection
Inspect the mechanical and electrical installation of the converter module visually to
ensure safe testing and use of the drive.
Cabinet construction
Checks for cabinet construction are listed below.
Instrumentation, busbars and cabling
Checks for instrumentation, busbars, cabling, clearances and creepage distances
are listed below. For more information, refer to ACS800-04/04M/U4 Hardware
Manual [3AFE64671006 (English)]: Planning the electrical installation.
Step Check item
1 Cabinet construction
1.1 Frame, wall, floor and roof structures, busbar enclosures and cable entries are correct and completely
assembled.
1.2 Mechanical joints are tightened and not broken.
1.3 Parts are clean and painted surfaces not scratched.
The cabinet frame and parts which are in metal to metal contact with the frame (e.g. seams,
component fixing points on assembly plates, back of control panel mounting plate) are not finished
with non-conducting paint or material.
1.4 IP enclosure class
1.5 There is a sufficient number of supports, bolts and nuts for cables.
Step Check item
2 Instrumentation
2.1 Type and number of option modules and other equipment is correct. Option modules and other
equipment are not damaged.
2.2 Option modules and terminals are labelled correctly.
2.3 The placement of option modules and other equipment inside the cabinet and on the cabinet door is
correct.
2.4 The mounting of option modules and other equipment is correct.