2.3. Project planning
Careful project planning is necessary before a HVC 450 kW E-Bus Charger is purchased and
put into operation. The different phases of the full project plan are shown in the figure below:
A. Preparation
The owner / site operator has ordered a HVC 450 kW E-Bus Charger. In this phase all
preparation work must be done before the contractor can do the civil and electrical
works. See About preparation on Page 24.
B. Construction
The contractor does all civil and electrical works. See About construction on Page 35.
C. Placement and Connection
The location is mechanically and electrically ready to receive the HVC 450 kW E-Bus
Charger. See About placement and connection on Page 51.
D. Commissioning
The delivery department will bring the HVC 450 kW E-Bus Charger into operation. See
Commissioning preparation on Page 109.
E. Service and Maintenance
The HVC 450 kW E-Bus Charger is in operation. There are various options for service
and maintenance. See About Service and Maintenance on Page 111.