HVC 450 kW E-Bus Charger Installation Guide
Revision: 1.2 COMPANY CONFIDENTIAL
Date released: 16-08-2018 Page 52 of 128
C7 Connect the GND wire to the ABB Pole on Page 89 and Connect cables ACS Control
Module on Page 91.
C8 Install masks plate work on Page 103 and Grouting of the pole construction on Page
108.
5.2. Route the cables
1. Unpack the cables. See Cabling on Page 46 for details which cables must be used.
2. Remove the top cover plate (B) and the front cover plate (C) from the foundation (A) by
loosen the bolts (D).
3. Put the front cover plate (C) and its bolts (D) in a safe location as it will be installed again
later on.
4. Route the DC power cables through the 6.30 Inch cable conduit.
5. Route the AC utility power, GND wire and Interlock cable through the other 6.30 Inch
cable conduit.
6. Route the communication glass fiber cable through the extra 1.58 Inch cable conduit.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB HVC and is the answer not in the manual?

ABB HVC Specifications

General IconGeneral
BrandABB
ModelHVC
CategoryBattery Charger
LanguageEnglish

Related product manuals