HVC 450 kW E-Bus Charger Installation Guide
Revision: 1.2 COMPANY CONFIDENTIAL
Date released: 16-08-2018 Page 91 of 128
2. Strip 0.79 Inch of the insulation from the end of the wire.
3. Attach a wire end ring (A) to the end of the GND wire (B).
4. Remove the M8 bolt and washers from the GND rail.
5. Fit the bolt (C) with toothed washer (D), the GND wire (B) and the contact washer (E).
6. Insert the bolt fitted with the GND wire into the GND rail.
7. Tighten the bolt with a tightening torque of 11.06 ft-lb.
5.15.5. Install lighting protection
1. Cut the wire of the lighting protection cable to the correct length to reach the lighting
protection connection on one of the each side of the vertical frame. Do not make the wire
routing too tight, or too loose.
2. Strip 0.79 Inch of the insulation from the end of the wire.
3. Attach a wire end ring (A) to the end of the lighting protection wire (B).
4. Remove the M8 bolt and washers from the lighting protection rail.
5. Fit the bolt (C) with toothed washer (C), the lighting protection wire (B) and contact washer
(E).
6. Insert the bolt fitted with the lighting protection wire into the lighting protection connection.
7. Tighten the bolt with a tightening torque of 11.06 ft-lb.
5.16. Connect cables ACS Control Module

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB HVC and is the answer not in the manual?

ABB HVC Specifications

General IconGeneral
BrandABB
ModelHVC
CategoryBattery Charger
LanguageEnglish

Related product manuals