Section-6
04-3004_S6_OPM_ABB_POWERSCALE_10-50 kVA_EN_150113.doc Page 1/6 ABB
Printed in Switzerland – Modifications reserved
CONTENTS SECTION-6
6.1 MULTI-CABINET CONFIGURATION .......................................................................................................... 2
6.1.1 CONCEPT OF MULTI-CABINET CONFIGURATION .......................................................................... 2
6.1.2 INSTALLATION INSTRUCTIONS ........................................................................................................ 3
6.1.2.1 Introduction ................................................................................................................................... 3
6.1.2.2 Paralleling of UPS-Cabinets ......................................................................................................... 3
6.1.2.2.1 Connection of Parallel Communication Cables (BUS-lines) ..................................................... 3
6.1.2.2.2 Parallel Adapter and DIP-Switch SW2-2 .................................................................................. 4
6.1.2.3 DIP-Switch SW1-9 Settings .......................................................................................................... 4
6.1.2.4 DIP Switch SW1-9 ........................................................................................................................ 4
6.1.2.5 ON/OFF – Main Buttons ............................................................................................................... 5
6.1.2.6 Parallel Isolator (IA2) .................................................................................................................... 5
6.1.2.7 Maintenance Bypass (IA1) ............................................................................................................ 5
6.1.2.7.1 Redundant Parallel Configuration ............................................................................................. 5
6.1.2.7.2 Capacity Parallel Configuration ................................................................................................ 5
6.1.2.8 ECO-MODE (BYPASS MODE) in Parallel Systems ..................................................................... 5
6.1.3 COMMISSIONING OF PARALLEL CONFIGURATION ....................................................................... 6
6.1.3.1 Start-up of a Parallel Configuration ............................................................................................... 6
6.1.3.2 Shutdown of Parallel Configuration .............................................................................................. 6