11.13.2.2 Testing the liquid medium supervision for temperature alarm and
temperature lock out conditions
GUID-189AF20B-D0E3-453D-A787-68F25D0903D3 v1
1. Consider the analogue temperature input SENTEMP and set
SENTEMP to a
value higher than TempAlarmLimit, check that outputs TEMPALM and ALARM
are activated after a set time delay of tTempAlarm.
2. Temperature lockout input SETTLO can be used to set TEMPLO signal.
3. Also, increase further the temperature input above TempLOLimit, check that
the outputs TEMPLO and LOCKOUT appears after a set time delay of
tTempLockOut.
4. Activate BLOCK binary input and check that the outputs TEMPALM, TEMPLO,
ALARM and LOCKOUT disappear.
5. Reset the BLOCK binary input.
6. Make sure that temperature lockout condition exists and then activate the
reset lock out input RESETLO and check that the outputs TEMPLO and
LOCKOUT reset.
11.13.2.3 Completing the test
GUID-1A0D8AF0-4C48-45E8-B31D-96734ED1A4D2 v1
Continue to test another function or end the test by changing the TestMode setting
to Off. Restore connections and settings to their original values, if they were
changed for testing purposes.
11.13.3 Breaker monitoring SSCBR
GUID-10D26C82-79FF-4EAD-AE4A-2F2DBE965087 v2
Prepare the IED for verification of settings outlined in section “Testing the IED
operation”.
The Signal Monitoring tool in PCM600 shows the service values that are available
on the Local HMI as well.
Values of the logical signals belong to the breaker monitoring are available on the
local HMI under: Main menu/Test/Function status/Monitoring/
BreakerMonitoring/SSCBR:x
11.13.3.1 Verifying the settings
GUID-962A344D-5F8D-49A6-B3AC-29C7FEED0A3D v4
1. Connect the test set for the injection of a three-phase current to the appropriate
current terminals of the IED.
2. If current need to be injected for a particular test, it should be done in the
phase selected by the PhSel parameter.
3. Follow the sequence for positioning the auxiliary contacts before testing:
POSCLOSE 0 1 0
POSOPEN 0 0 1
4. Test of CB contact travel time
Section 11 1MRK 505 378-UEN A
Testing functionality by secondary injection
262 Line differential protection RED670 2.2 IEC
Commissioning manual