EPSON Stylus C67/C68/D68 Revision A
DISASSEMBLY/ASSEMBLY Overview 38
4.1.4 Work Completion Check
If any service is made to the printer, use the checklist shown below to confirm all
works are completed properly and the printer is ready to be returned to the user.
Table 4-3. Work Completion Check
Classification Item Check Point Status
Main Unit
Self-test Is the operation normal?
Checked
Not necessary
ON-line Test Is the printing successful
Checked
Not necessary
Printhead
Is ink discharged normally from all
the nozzles?
Checked
Not necessary
Carriage
Mechanism
Does it move smoothly?
Checked
Not necessary
Is there any abnormal noise during
its operation?
Checked
Not necessary
Is there any dirt or foreign objects on
the CR Guide Shaft?
Checked
Not necessary
Is the CR Motor at the correct
temperature? (Not too hot to touch?)
Checked
Not necessary
Paper Feeding
MEchanism
Is paper advanced smoothly?
No paper jamming?
No paper skew?
No multiple feeding?
No abnormal noise?
Checked
Not necessary
Is the PF Motor at correct
temperature?
Checked
Not necessary
Is the paper path free of any
obstructions?
Checked
Not necessary
Adjustment
Specified
Adjustment
Are all the adjustment done
correctly?
Checked
Not necessary
Lubrication
Specified
Lubrication
Are all the lubrication made at the
specified points?
Checked
Not necessary
Is the amount of lubrication correct?
Checked
Not necessary
Function ROM Version Version:
Checked
Not necessary
Packing
Ink Cartridge
Are the ink cartridges installed
correctly?
Checked
Not necessary
Protective
materials
Have all relevant protective
materials been attached to the
printer?
Checked
Not necessary
Others
Attachments,
Accessories
Have all the relevant items been
included in the package?
Checked
Not necessary
Table 4-3. Work Completion Check
Classification Item Check Point Status