8-98 Section 8-2 - DISASSEMBLY/RE-ASSEMBLY
8-2-42 ECG Cable Hook
8-2-42-1 Tools
• Common pilIips screwdrivers
8-2-42-2 Removal procedure
1.) Unscrew 2 screws (1-2) to remove the ECG Cable Hook.
2.) Perform the following functional tests. If all are successful, include the debrief script provided below.
8-2-42-3 Mounting Procedure
Install the new parts in the reverse order of removal.
Figure 8-132 Screws of cable hook
Table 8-43 Functional Tests
Service Manual
Section
Functional Test / Diagnostic Test Debrief Script
Section 4-3-1
Power On/Boot Up
“Service Manual, Direction
5394141, Rev 1+, Section 8-2-42. Equipment
passed all required tests and is ready for use. “
Section 4-3-2
Power Off / Shutdown
Section 4-8-1
Cover Parts Function Validation
Section 10-5-5
Physical Inspection