EasyManuals Logo
Home>Gree>Inverter>GMV-S120WL/A-S

Gree GMV-S120WL/A-S User Manual

Gree GMV-S120WL/A-S
391 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #165 background imageLoading...
Page #165 background image
GMV5 Home DC Inverter Multi VRF Units
159
2)Use the perfusing duct to connect the regulator valve and vacuum pump to detection
connectors of the gas pipe valve, liquid pipe valve and high-pressure gas pipe valve.
3)Vacuumize for 4 hours and check whether the vacuum degree reaches -0.1MPa or more. If
not, leakage may exist. Perform leakage check again. If no leakage exists, continue to vacuumize
for 2 hours.
4)If the vacuum degree cannot be kept after vacuumization is performed for twice, there may
be water in the pipe when it is confirmed that no leakage exists. In this case, discharge water by
means of vacuum breaking. Perfuse nitrogen at 0.05MPa to the pipe. Vacuumize for 2 hours and
keep vacuuming for 1 hour. If the vacuum degree of -0.1MPa cannot be reached, repeat this
operation till water is discharged.
5)After vacuumization, turn off the regulator valve and keep for 1 hour. Ensure that the
pressure of the regulator valve does not increase.
9.5.1.4.2 Precautions:
1) Arrange vacuumization from the gas pipe and liquid pipe simultaneously and then arrange
vacuumization from the high-pressure gas pipe.
Check if the gas pipe valve, liquid pipe valve and high pressure gas pipe valves of ODU
connected with IDU and hydro box are fully closed.
As shown below, discharge air with vacuum pump from the gas pipe valve, liquid pipe valve
and high pressure gas pipe valves of ODU. If all IDUs and ODU are energized, the unit can enter
vacuum pumping mode of IDUs, ensuring that the valves of IDU and hydro box are open.
2)Turn off the valve before powering off the vacuum pump.
3)Keep vacuuming for 2 hours. The vacuum meets the requirement if the pressure displayed
by the vacuum gauge does not increase.
9.5.2 Insulation for the refrigerant system pipe
9.5.2.1 Insulation materials
Use closed-cell foam insulation materials with flame retardant grade of B1.
The heat conductivity is not greater than 0.035 w/(m·k) when the average temperature is 0°C.
9.5.2.2 Thickness of the insulation layer
External Diameter of the Pipe (mm)
≤12.7
≥15.88
Thickness of the Insulation Layer (mm)
≥15
≥20
Use sunblock, anti-weathering, and non-cracking insulation materials for outdoor pipes.
9.5.2.3 Procedure of insulation
1)Select insulation materials based on design requirements.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Gree GMV-S120WL/A-S and is the answer not in the manual?

Gree GMV-S120WL/A-S Specifications

General IconGeneral
BrandGree
ModelGMV-S120WL/A-S
CategoryInverter
LanguageEnglish

Related product manuals