3.3 Inspection before Commissioning
Caution!
Check Table before Commissioning
Checkup of
installation
drawing
Check if the engineering design
drawing is complete.
Check if the construction is
conducted according to design
drawing.
Checkup of
installation
environment
Check if there is pollution source
around installation place of outdoor
unit, whether the selection of
installation position of outdoor unit
is correct.
Refer to installation
of outdoor unit
Check if basement of outdoor unit is
firm enouph? Whether its damping
and drainage comply with the
requirement?
Refer to installation
of outdoor unit
Check if the outdoor unit is operated
with static pressure? Whether it has
been set with corresponding static
pressure?
Checkup of
cooling system
Check if the capacity of indoor unit
accounts for 80%~100% of rated
capacity of outdoor unit?
Check if pipeline of refrigerant and
water pipe are in conformity with the
requirements?
Refer to installation
requirements
Check if the height difference
between indoor unit and outdoor
unit meet the design requirement of
unit?
Height difference
when outdoor unit is
in upper
position40m
Height difference
when outdoor unit is
in lower