6 Check Before Power-On
Table 6-1 Installation checklist
No. Check Item Acceptance Criteria
1 SUN2000 installation The SUN2000 is installed correctly,
securely, and reliably.
2 Smart Dongle The Smart Dongle is installed correctly
and securely.
3 Cable layout Cables are routed properly as required
by the customer.
4 Cable tie Cable ties are secured evenly and no
burr exists.
5 Grounding The ground cable is connected
correctly, securely, and reliably.
6 Turn o the switches The DC SWITCH and all the switches
connected to the SUN2000 are set to
OFF.
7 Cable connections The AC output power cable, DC input
power cable, and signal cable are
connected correctly, securely, and
reliably.
8 Unused terminals and ports Unused terminals and ports are locked
by watertight caps.
9 Installation environment The installation space is proper, and
the installation environment is clean
and tidy, without foreign matter.
SUN2000-(8K, 10K)-LC0 Series
User Manual 6 Check Before Power-On
Issue 01 (2023-09-15) Copyright © Huawei Digital Power Technologies Co., Ltd. 74

Table of Contents

Other manuals for Huawei SUN2000-8K-LC0

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei SUN2000-8K-LC0 and is the answer not in the manual?

Huawei SUN2000-8K-LC0 Specifications

General IconGeneral
BrandHuawei
ModelSUN2000-8K-LC0
CategoryInverter
LanguageEnglish

Related product manuals