7.3 Setting Functions and Features Through Device
Commissioning
● The grid-connection voltage and frequency of inverters in China are set before
delivery according to NB/T 32004 or the latest Chinese standard. If the inverter
fails to connect to the power grid because the power grid voltage is close to or
higher than the voltage required by Chinese laws and regulations, you can
select other voltage level after obtaining permission from the local power
operator.
● If the power grid voltage exceeds the upper threshold, the service life of loads
on the grid side may be aected, or energy yield loss may occur. In this case,
the Company will not be liable for any consequences.
Choose Commission Device and set related device parameters.
● For details about the commissioning portal when the Smart Dongle
networking is used, see B Connecting the Inverter on the App.
● For details about the commissioning portal when the EMMA networking is
used, see C Connecting the EMMA on the App.
7.3.1 Setting Common Parameters
Set common parameters based on the devices connected to the plant.
SUN2000-(8K, 10K)-LC0 Series
User Manual 7 Power-On and Commissioning
Issue 01 (2023-09-15) Copyright © Huawei Digital Power Technologies Co., Ltd. 82