Before switching on
8
Commissioning
8.2
L
8.2-1
EDS82EV903-1.0-11/2002
8.2 Before switching on
)
))
) Note!
l Do not change the switch-on sequence.
l In the event of an error during commissioning please see the
chapter ”Fault detection and elimination”.
Check the following to avoid damage to persons or material...
...before the mains voltage is connected:
l Wiring for completeness, short circuit and earth fault
l ”Emergency-off” function of system
l Motor connection (star/delta) must be adapted to output voltage of
controller.
l If you do not use a function module ensure that the FIF cover is mounted
properly (as delivered).
l If the internal voltage supply is connected, for instance, to X3/20 of the
standard-I/O, terminals X3/7 and X3/39 must be bridged.
... the most important drive parameter settings before the controller is enabled:
l Are the drive parameters relevant for your application set correctly?
– e. g. configuration of analog and digital inputs and outputs