6-2
6-2 Preparing for Operation
6
Operation
6-2 Preparing for Operation
This section explains the procedure to prepare the mechanical system for trial operation after the
installation and wiring of the Servomotor and Servo Drive are completed. It also explains the items
that need to be checked before and after turning ON the power.
Items to Check Before Turning ON the Power
îš„ Checking Power Supply Voltage
 Check to be sure that the power supply voltage is within the ranges shown below.
R7D-BP@@L (Single-phase 100 VAC input)
Main-circuit power supply: Single-phase 100/115 VAC (85 to 127 V) 50/60 Hz
R7D-BP@@H (Single-phase/three-phase 200 VAC input)
Main-circuit power supply: Single-phase/three-phase 200/240 VAC (170 to 264 V) 50/60 Hz
R7D-BP@@HH (Single-phase 200 VAC input)
Main-circuit power supply: Single-phase 200/240 VAC (170 to 264 V) 50/60 Hz
îš„ Checking Terminal Block Wiring
 The main-circuit power supply input lines (L1/L3 or L1/L2/L3) must be properly connected to the
terminal block.
 The Servomotor's red (U), white (V), and blue (W) power lines and the green/yellow ground wire
( ) must be properly connected to the terminal block.
îš„ Checking the Servomotor
 There should be no load on the Servomotor. (Do not connect the mechanical system.)
 The Servomotor’s power lines and the power cables are securely connected.
 The Encoder Cable must be securely connected to the Encoder Connector (CN2) at the Servo
Drive.
 The Encoder Cable must be securely connected to the Encoder Connector at the Servomotor.
îš„ Checking the I/O Control Connectors
 The Control Cable must be securely connected to the I/O Control Connector (CN1).
 The RUN Command Input (RUN) must be OFF.
îš„ Checking Parameter Unit Connections
 The Parameter Unit (R88A-PR02G) must be securely connected to the CN3 connector.
Turning ON Power
 After checking the above items, turn ON the main circuit power supply.
 The alarm output (ALM) will take approximately 2 seconds to turn ON after the power has been
turned ON. Do not attempt to detect an alarm using the Host Controller during this time (when
power is being supplied with the Host Controller connected).

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Omron SMARTSTEP 2 SERIES and is the answer not in the manual?

Omron SMARTSTEP 2 SERIES Specifications

General IconGeneral
BrandOmron
ModelSMARTSTEP 2 SERIES
CategoryDC Drives
LanguageEnglish

Related product manuals