2-2 Drive Start Up
Drive Start Up Checklist
This checklist contains the major steps required to complete the drive
commissioning procedure.
❏ 1. Verify all Drive Configuration Settings - page 2-2
.
❏ 2. Verify the Power Wiring - page 2-2
.
❏ 3. Verify the Control and I/O Wiring - page 2-3
.
❏ 4. Apply Voltage to the Control Circuits - page 2-4
.
❏ 5. Verify the Control Voltages - page 2-5
.
❏ 6. Load the Default Settings - page 2-6
.
❏ 7. Configure the Most Commonly Used Parameters - page 2-6
.
❏ 8. Tune the Current Regulator - page 2-10
.
❏ 9. Verify Motor Rotation and Run Feedback Polarity Checks -
page 2-11
.
❏ 10. Configure the Speed Feedback Parameters - page 2-14
.
❏ 11. Tune the Speed Regulator - page 2-15
.
❏ 12. Verify Speed Reference Settings and Drive Operation - page 2-16
.
Before Applying Power to
the Drive
1. Verify all Drive Configuration Settings:
1. With the bottom cover removed from the drive (refer to Removing
the Drive Covers on page 1-7), verify that DIP switch S14 is set
correctly to be ≥ the rated field current specified on the motor
nameplate. Refer to Table 1.G on page 1-25
.
2. Verify all switch settings (S9, S10, and S11) for the analog inputs.
Refer to Table 1.L on page 1-33
.
3. Verify all DIP switch and jumper settings for the digital encoder or
analog tachometer feedback device. Refer to Table 1.L on
page 1-33 and Figure 1.30 on page 1-34.
2. Verify the Power Wiring:
Verify that the AC line power at the disconnect device is within the
rated value of the drive and that all power wiring is correct. Refer to
Power Wiring on page 1-15
for further information.
!
ATTENTION: The Drive can overspeed if DIP switch S4 is set
incorrectly, or the tachometer is wired incorrectly. Failure to
observe this precaution could result in damage to, or destruction
of, the equipment.
!
ATTENTION: Do not connect any external power to the
armature output terminals, personal injury and/or equipment
damage can occur.