4 Installation
4.1 General installation procedure
Preliminary requirements
1. All required permits to agree
with the local rules are
granted.
2. The AC input cable is
available.
• There is no voltage on the AC
input cable during the
complete installation
procedure.
• Tools for installation. Refer to
section
11.6
.
Procedure
1. Unpack the EVSE. Refer to section
4.2
.
2. Prepare the site. Refer to chapter
5
.
3. Remove the cabinet cover. Refer to section
9.1
.
4. Do the mechanical installation. Refer to section
6.1
.
5. Do the electrical installation. Refer to section
7.1
.
6. Install the cabinet cover. Refer to section
9.2
.
7. Do the commissioning procedure. Refer to section
8.1
.
4.2 Unpack the EVSE
1. Open the box.
2. Remove the EVSE from the box.
3. Remove all packaging material from the EVSE.
4. Discard the packaging material. Refer to section
3.8
.
5. Make sure that all parts are delivered according to the order. Refer to the order and
section
11.4
.
6. Do an inspection of the EVSE and the parts for installation for damage.
7. If you find damage or the parts are not according to the order, contact the local
representative of the manufacturer (ABB EV Infrastructure).
Installation
BCM.V3Y01.0-EN | 001 27