Grove Published 4-09-2021, Control # 364-11 4-17
RT765E-2 OPERATOR MANUAL SET-UP AND INSTALLATION
15. Raise the boom to horizontal and extend the boom just
enough to clear the extension stowage lugs from the
guide ramps and stowage pins on the front and rear
stowage brackets.
16. Remove the hitch pin and clip pin securing the boom
extension alignment device in the stowed position. Pull
the push bar assembly out to the working position and
secure it in place with the hitch pin and clip pin.
17. Slightly raise and/or lower the boom to help control the
extension. Using the rope attached to the tip of the
extension, swing the extension into place ahead of the
boom nose, engaging the anchor fittings with the
attachment fittings on the left side of the boom nose.
STOWED POSITION
WORKING POSITION
6658-2
1
2
3
4
5, 6
5, 6
4
3
2
1
Item Description
1 Pusher Bar
2 Collar Clamp
3 Adjustment Bar
4 Push Bar Assembly
5 Hitch Pin
6 Clip Pin
FIGURE 4-12 continued
CAUTION
If the fly section remains on the extension base, do not
extend the extension assembly to far, as the nose of the
extension fly section could contact the front stowage
bracket and cause damage.
DANGER
When erecting the boom extension, ensure that all
personnel and equipment are kept clear of the swing path.