Inspection of the installation
Current regulations require the heating installation to be inspected before it is commissioned. The inspection must be
carried out by a suitably qualified person. Fill in the page for information about installation data in the User manual.
DateSignatureNotesDescription
Connecting to air/water heat pump
System flushed
System vented
Expansion vessel
Particle filter
Safety valve
Shut off valves
Boiler pressure
Connected according to outline diagram
Flows according to table in section "Minimum
system flows", chapter "Pipe connections"
Cold and hot water
Shut off valves
Mixing valve
Safety valve
Electrical connections
Connected communication
Circuit fuses
Fuses, indoor module
Fuses property
Outside sensor
Room sensor
Current sensor
Safety breaker
Earth circuit-breaker
Setting emergency mode
Miscellaneous
Docked to