BRIDGE UNIT FOR MAILBOX INSTALLATION (G912)
G065 1-28 SM
1.11.2 INSTALLATION PROCEDURE
!
CAUTION
Unplug the main machine power cord before starting the following
procedure.
NOTE: The bridge unit for the mailbox must be installed when both the mailbox
and a finisher will be installed. Install the mailbox first, then this bridge unit,
and finally the finisher
1. Unpack the bridge unit and remove the shipping retainers [A].
NOTE: Do not remove the protective sheet [B] at this time.
2. Remove the mailbox if it has been installed.
3. Remove the rear cover [C] of the mailbox (! x 8).
4. Remove the proof tray unit [D] (! x 6, " x 1).
5. Remove the cover [E].
G909I508.WMF
G912I506.WMF
[C]
[E]
[A]
[B]
[A]
[D]