Step 3: Verifying Proper Activation
Afterthewake-uptimeisover,astatusscreensimilartothefollowingappearsontheinverterLCDpanel:
V a c [ V ] V d c [ V ] P a c [ W ]
2 4 0 . 7 3 7 1 . 9 2 3 4 9 . 3
P _ O K : X X X / Y Y Y < S _ O K >
. . . . . . . . . . . . . . . . . O N
1. Verifythefollowing:
l ThegreeninverterLEDissteadilylit.
l TheON/OFFindicatorontheLCDpanelreadsON.
l P_OK: XXX/YYY:Thereisaconnectiontothepoweroptimizersandatleastonepoweroptimizeris
sendingmonitoringdata.Optimizerssendtelemetriesinafrequencyofupto10minutes.
l S_OK appears,iftheinverterisconnectedtotheSolarEdgemonitoringplatform.
l Vac [V]specifiesthemeasuredgridACoutputvoltage.
l Vdc [v] :SpecifiestheDCinputvoltage,whichshouldequalthesumoftheoutputvoltagesofall
modules(andshouldbewithintheoperatingrangeoftheinverter).
l Pac [W]specifiestheACoutputpowerproduced.
2. Takenoteoftheserial#ontheinverterlabelusingthedetachable2Dbarcodestickeroneachdevice.
ThisinformationisusedintheSolarEdgemonitoringplatformtoidentifythisinverterandisneeded
toopenanewsiteinthemonitoringplatform.
YourSolarEdgepowerharvestingsystemisnowoperational.
Step 4: Reporting and Monitoring Installation Data
NOTE
This step requires connecting one of the communication options. Refer to Setting Up
Communication to the Monitoring Platform on page 69.
The SolarEdge Monitoring System
TheSolarEdgecloud-basedmonitoringplatform(monitoringplatform)enablesaccessing
SolarEdgesiteinformation,includingup-to-dateinformationviewedinaphysicalor
logicalview.ThemonitoringplatformisdescribedindetailintheSolarEdgeMonitoring
PlatformUserGuide,availableontheSolarEdgewebsiteat
http://www.solaredge.us/files/pdfs/solaredge-monitoring-platform-user-guide.pdf.The
SolarEdgemonitoringplatformcandisplaylogicalandphysicallayoutsoftheinstalled
system,asfollows:
l Logical Layout:Showsaschematiclogicallayoutofthecomponentsinthesystem,suchas:inverters,
stringsandmodules,aswellastheirelectricalconnectivity.Thisviewenablesyoutoseewhich
modulesareconnectedineachstring,whichstringsareconnectedtoeachinverter,andsoon.
l Physical Layout:Showsaschematicphysicallayoutofthecomponentsinthesystem,suchas:
inverters,stringsandmodules,aswellastheirelectricalconnectivity.Thisviewenablesabird’seye
viewoftheactuallocationofasystemcomponent.