Eaton 9155 UPS (8–15 kVA) User’s Guide 164201553—Rev H0 61
Figure 46. Removing Knockout Tabs
4. Route the cable(s) to the approximate location of the cover access holes.
5. Connect the cables to the appropriate location.
See paragraph 6.2 Communication Options or 6.3 Control Terminals for detailed information.
6. Reinstall the front covers, starting with the bottom cabinet (see Figure 47).
Hang the top edge of the cover on the cabinet first, then lower the bottom edge and snap into place. Be
sure the cables fit in the access holes in the covers.
7. Continue to Chapter 7 UPS Operating Instructions to start up the UPS.