EasyManuals Logo
Home>Trane>Chiller>CGAM

Trane CGAM User Manual

Trane CGAM
276 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #24 background imageLoading...
Page #24 background image
24 CG-SVX17D-EN
Pre-Installation
Installation Requirements
A list of the contractor responsibilities typically associated with the unit installation process is
provided.
Type of
Requirement
Trane Supplied
Trane Installed
Trane Supplied
Field Installed
Field Supplied
Field Installed
Foundation Meet foundation requirements
Rigging
Safety chains
Clevis connectors
•Lifting beam
Isolation
Elastomeric isolators
(optional)
Elastomeric isolators (optional)
Electrical
•Circuit breakers
(optional)
Unit mounted starter
Circuit breakers (optional)
Electrical connections to unit mounted starter
Wiring sizes per submittal and NEC
Terminal lugs
Ground connection(s)
BAS wiring (optional)
Control voltage wiring
Chilled water pump contactor and wiring including interlock
Option relays and wiring
Water piping
Flow switch
Water strainer
Taps for thermometers and gauges
Thermometers
Water flow pressure gauges
Isolation and balancing valves in water piping
Vents and drain
Pressure relief valves
Insulation
Insulation
High humidity
insulation (optional)
•Insulation
Water Piping
Connection
Components
•Grooved pipe
Other Materials
R-410A refrigerant (1
lb. maximum per
machine as needed)
Dry nitrogen (20 psig
maximum per
machine as needed)

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Trane CGAM and is the answer not in the manual?

Trane CGAM Specifications

General IconGeneral
BrandTrane
ModelCGAM
CategoryChiller
LanguageEnglish

Related product manuals