Planning the installation 41
Tools needed during installation
Depending on the system size, selected mounting location and materials used,
mechanical and electrical installers could need the following equipment and tools:
General tools
Personal safety equipment such as gloves, helmet, goggles, ear plugs, safety
harness etc.
Step ladders.
•Knife.
Tools for mechanical installation
Equipment for transporting and lifting the inverter.
Electric (hammer) drill.
•Hammer.
Set of drill bits, wrenches, sockets and screw bits.
Socket driver, screwdriver.
Tape measure.
Spirit level.
Pencil or other marker.
Fastening screws, plugs, etc.
Tools for electrical installation
Hexagonal driver 3mm for securing the front cover and AC connector.
Flat screwdriver 3mm for releasing spring terminals.
Cable and wire strippers.
Side cutters.
Crimping tool and cable lugs.
Cable marking equipment.
Multicontact MC4 cabling tool set or MC adapter set.
Digital multimeter (insulation tester) with DC and AC sensitive current clamp,
voltage measurement (max. 1000 VDC) and continuity testing functions.

Table of Contents

Other manuals for ABB PVS300

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB PVS300 and is the answer not in the manual?

ABB PVS300 Specifications

General IconGeneral
BrandABB
ModelPVS300
CategoryInverter
LanguageEnglish

Related product manuals