1756-6.5.3 - December 1999
8-22 PLC-5C to Logix5550 Controller: Scheduled Communications
Schedule the Network
Whenever you change the network configuration you must run RSNetWorx
for ControlNet to reschedule the network.
1. Restore RSNetWorx for ControlNet and click on the Enable Edits box.
2. From the Selection menu, select Survey Network.
3. Save the RSNetWorx for ControlNet configuration file.
The following prompt will appear:
4. Select “Optimize and re-write schedule for all connections” and click on
OK.
5. Minimize RSNetWorx for ControlNet.

Table of Contents

Other manuals for Allen-Bradley ControlLogix

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Allen-Bradley ControlLogix and is the answer not in the manual?

Allen-Bradley ControlLogix Specifications

General IconGeneral
BrandAllen-Bradley
ModelControlLogix
CategoryIndustrial Electrical
LanguageEnglish

Related product manuals