Test Operation ESIE09-08B
70 Test Operation
1. Test Operation
1.1 Procedure and Outline
Follow the following procedure to conduct the initial test operation after installation.
1.1.1 Check Work Prior to Turn Power Supply On
Check on refrigerant piping
(V3180)
Check on amount of refrigerant
charge
Check air tight test and vacuum
drying
Check on water piping
Check the below items.
Power wiring
Control transmission wiring
between units
Earth wire

Table of Contents

Other manuals for Daikin Altherma HT

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Daikin Altherma HT and is the answer not in the manual?

Daikin Altherma HT Specifications

General IconGeneral
TypeAir-to-water heat pump
RefrigerantR-410A
Water Outlet TemperatureUp to 80°C
Operating Temperature Range-20°C to 35°C
Power Supply3-phase, 400V
Energy Efficiency Class (Heating)A++

Related product manuals