EasyManuals Logo
Home>GE>Relays>T35

GE T35 User Manual

GE T35
610 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #527 background imageLoading...
Page #527 background image
CHAPTER 8: COMMISSIONING INRUSH INHIBIT TEST
T35 TRANSFORMER PROTECTION SYSTEM – INSTRUCTION MANUAL 8-13
8
8.3 Inrush inhibit test
8.3.1 Inrush inhibit test procedure
The Inrush Inhibit Test requires a secondary injection test capable of producing a current with an adjustable second
harmonic component. Use the appropriate commissioning tables at the end of this chapter to record values.
This procedure is based upon the example provided in the Differential Characteristic Test Example section. The transformer
parameters are as follows.
• Transformer data — Y/y0°, 230/69 kV, CT1 (300:1), CT2 (1000:1)
• 2nd Harmonic Setting — 20%
1. Connect the relay test set to inject current into the Winding 1 Phase A CT input.
2. Inject currents into the relay as shown in the following table until the biased differential element picks up.
3. Confirm that only the percent differential element has operated.
4. Increase the harmonic content until the element drops out. Record this value as the Inrush Inhibit Level Pickup.
5. Gradually decrease the harmonic content level until the element picks up. Record this value as the Inrush Inhibit Level
Dropout.
6. Switch off the current.
7. Repeat steps 1 through 6 for phases B and C.
8. Repeat steps 1 through 7 for Winding 2 (and Windings 3 and 4 if necessary).
Table 8-3: Inrush inhibit test summary
The second harmonic inhibit feature can be verified by setting the
INRUSH INHIBIT MODE setting as follows.
For
INRUSH INHIBIT MODE set to "2-out-of-3":
1. Set the
INRUSH INHIBIT FUNCTION to "Trad. 2nd" and the INRUSH INHIBIT LEVEL to "20%".
2. Inject currents into one CT bank (one winding only) until the biased differential operates for all three phases.
3. Apply a second harmonic to Phase A higher than the set threshold and monitor operation of Phases A, B, and C. The
element needs to remain operating on all three phases.
4. Apply a second harmonic to Phase B with a level less than the set threshold.
5. Increase the second harmonic level in Phase B. When it passes the set threshold, all three phases of differential
protection need to drop out.
For
INRUSH INHIBIT MODE set to "Average":
1. Set the
INRUSH INHIBIT FUNCTION to "Trad. 2nd" and the INRUSH INHIBIT LEVEL to "20%".
2. Inject currents into one CT bank (one winding only) until the biased differential operates for all three phases.
3. Apply a second harmonic to Phase A with a level greater than the set threshold and monitor the operation of the
Percent Differential element. The element should drop out when the injected second harmonic level becomes three
times larger than the set threshold.
Phase Injected Displayed Status
W1 Current W1 2nd
Harmonic
W2 Current W2 2nd
Harmonic
I
d
2nd
Harmonic
I
r
A1 A ∠0° 18.01% 0 A ∠0° 0 0.997 pu 18% 0.997 pu Operate
1 A ∠0° 19.97% 0 A ∠0° 0 0.997 pu 20% 0.997 pu Block
B4 A ∠0° 16.72% 2 A ∠–180° 15% 2 pu 18% 4 pu Operate
4 A ∠0° 17.60% 2 A ∠–180° 15% 2 pu 20% 4 pu Block
C2 A ∠0° 15% 4 A ∠–180° 16.3% 2 pu 18% 4 pu Operate
2 A ∠0° 15% 4 A ∠–180° 17.3% 2 pu 20% 4 pu Block

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE T35 and is the answer not in the manual?

GE T35 Specifications

General IconGeneral
BrandGE
ModelT35
CategoryRelays
LanguageEnglish

Related product manuals