10.22
Section 10
Reassembly
Figure 10-77. Installing Grass Screen.
Install Oil Sentry or Pipe Plug
1. Apply pipe sealant with Teflon
®
(Loctite
®
No.
59241 or equivalent), to the threads of the 1/8”
pipe plug or adapter. Install and tighten into the
port on the closure plate. See Figure 10-78. Torque
pipe plug to 4.5-5.0 N·m (40-45 in. lb.). If a switch
was installed, apply sealant to the threads of the
Oil Sentry™ switch and install into the adapter or
center passage. Torque the switch to 4.5-5.0 N·m
(40-45 in. lb.). Connect the green wiring harness
lead to the terminal on the switch. See Figure
10-79.
Figure 10-76. Installing Blower Housing Screws.
3. Snap the grass screen onto the cooling fan. See
Figure 10-77.
Figure 10-78. Installing Pipe Plug or Adapter.
Notch
Center Passage
Oil Sentry™
Switch
Figure 10-79. Installed Oil Sentry Switch.