TP-6714 4/1014 Section 1 Installation
1.5 System Setup
Set the controller’s current time and date. See
Section 5.6 for instructions.
The transfer switch is factory-set with default settings for
time delays and other parameters. To view the settings,
review the controller operation instructions in Section 3,
and then refer to Section 4.3 for instructions to view the
setup screens.
If it is necessary to change settings, see Section 5 for
instructions.
Note: Use caution when changing transfer switch
settings. The source voltage and frequency
settings must match the values shown on the
transfer switch nameplate.
1.6 Exerciser Setup
Set the exerciser to start and run the generator set at
least once a week. See Section 5.7 for instructions.
1.7 Functional Tests
Perform the functional tests described in the transfer
switch Installation Manual and in Section 2 of this
manual before putting the transfer switch into operation.
1.8 Warranty Registration
Complete a Startup Notification Form and submit it to
the manufacturer within 60 days of the initial startup
date. The Startup Notification Form covers all
equipment in the power system. Power systems not
registered within 60 days of startup are automatically
registered using the manufacturer’s ship date as the
startup date.