Installation
3-2
Part 1073401_07
E 2021 Nordson Corporation
Additional Information
This section presents installation procedures in their most commonly used
form. Procedural variations or special considerations are explained in the
additional information table that follows most procedures. Where applicable,
some table entries also contain crossâreference information. Additional
information tables are indicated by the symbol shown to the left.
Installation Tasks
The installation sequence is as follows:
1. Verify that the required installation conditions and utilities exist.
2. Unpack and inspect the melter.
3. Mount the melter on the parent machine or support structure.
4. Connecting the electrical service.
5. Connect hot melt hoses and applicators.
6. Set up the melter to work with the manufacturing process.
7. Install optional equipment.
8. (If used) Connect a applicator driver, pattern controller, or timer.
9. Flush the melter.
10. Adjust the pressure control valve.
Experience of Installation Personnel
The instructions provided in this section are intended to be used by
personnel who have experience in the following subjects:
S Hot melt application processes
S Industrial power and control wiring
S Industrial mechanical installation practices
S Basic process control and instrumentation