EasyManuals Logo

Siemens 1LA8 Operating Instructions

Siemens 1LA8
148 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #49 background imageLoading...
Page #49 background image
Shaft extensions with feather key
To maintain the balancing quality, you have the following options:
If the transmission element is shorter than the feather key with balancing type "H", then you
must machine off the section of feather key protruding from the shaft contour and
transmission element in order to maintain the balance quality.
If the transmission element is drawn up on to the shoulder of the shaft, you must ensure
that the part of the coupling groove where the feather key is not inserted is taken into
consideration when balancing the coupling.
The following applies for all 2-pole machines and 4-pole machines with a frequency ≥ 60 Hz:
The feather key must be shortened if the coupling hub is shorter than the feather key.
The center of gravity of the coupling half should be within the length of the shaft end.
The coupling used must be prepared for system balancing.
The number of poles of the machine is specified on the rating plate (in the designation of
the motor type).
WARNING
The feather key can fall out
The feather keys are only locked against falling out during shipping. If a machine with two
shaft extensions does not have an output element on one shaft extension, the feather key
can fall out during operation.
Death or serious injury can result.
Do not operate the machine unless the transmission elements have been pulled on.
On shaft extensions without output element, make sure that the feather key cannot fall
out and shorten it by approximately half for balance type "H".
5.2.6 Lifting and transporting the machine
To safely lift and transport the machine, the following requirements must be met:
Personnel operating cranes and fork-lift trucks must be appropriately qualified.
If the motor is packed, depending on the weight, size and on-site conditions, lift crates and
transport frames using a fork-lift truck or a crane with slings.
Use a crane or fork-lift truck suitable for the load.
The center of gravity of the goods and the positions of the hoisting points are indicated
on the packaging. Do not hoist any goods with damaged packaging.
When lifting the machine, use only approved and undamaged sling guides and spreaders
of sufficient rated capacity. Check the lifting equipment prior to its use. The weight of the
machine is shown on the rating plate.
Assembly
5.2 Lift the machine to where it will be installed, and position it
SIMOTICS TN Series N-compact 1LA8
Operating Instructions 05/2016 49

Table of Contents

Other manuals for Siemens 1LA8

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens 1LA8 and is the answer not in the manual?

Siemens 1LA8 Specifications

General IconGeneral
BrandSiemens
Model1LA8
CategoryEngine
LanguageEnglish

Related product manuals