Any supplementary motor monitoring devices and equipment have been correctly
connected and are functioning correctly.
All brakes and backstops are operating correctly.
At the monitoring devices, the values for "Warning" and "Shutdown" are set.
See also
Set values for monitoring the winding temperature (Page 84)
Setpoint values for monitoring the bearing temperature (Page 84)
Converter operation
If the design of the motor requires connection to a particular converter type, the rating plate
will contain corresponding additional information.
The converter is correctly parameterized. The parameterization data is specified on the
rating plate of the machine. Information about the parameters is available in the operating
instructions for the converter.
The specified limit speed n
max
is not exceeded. Limit speed n
min
is not fallen below.
Cooling
Check that the machine cooling is available for commissioning.
The bearing insulation should be executed as shown on the plates.
7.2 Measuring the insulation resistance before commissioning
Measuring the insulation resistance and polarization index (PI) provides information on the
condition of the machine. It is therefore important to check the insulation resistance and the
polarization index at the following times:
Before starting up a machine for the first time
After an extended period in storage or downtime
Within the scope of maintenance work
The following information is provided regarding the state of the winding insulation:
Is the winding head insulation conductively contaminated?
Has the winding insulation absorbed moisture?
As such, you can determine whether the machine needs commissioning or any necessary
measures such as cleaning and/or drying the winding:
Can the machine be put into operation?
Must the windings be cleaned or dried?
Detailed information on testing and the limit values can be found here:
"Testing the insulation resistance and polarization index" (Page 42)
Start-up
7.2 Measuring the insulation resistance before commissioning
SIMOTICS TN Series N-compact 1LA8
82 Operating Instructions 05/2016

Table of Contents

Other manuals for Siemens 1LA8

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens 1LA8 and is the answer not in the manual?

Siemens 1LA8 Specifications

General IconGeneral
BrandSiemens
Model1LA8
CategoryEngine
LanguageEnglish

Related product manuals