TB7300 Installation and Operation Manual Installation 67
© Tait International Limited December 2022
5.5.2 Equipment Required
It is beyond the manual’s scope to list everything required. However, the
following tools and equipment are specifically required for installing the
base station.
Tools ■ Philips #2 tip screwdriver used to connect the DC power cables to the
DC power terminals
■ Pozidriv PZ3 screwdriver for the M6 screws used to secure the tray to
the cabinet in Tait factory-assembled systems
■ 8mm spanner for the M5 nut on the ground connector
You can also obtain the TBA0ST2 tool kit from your regional Tait office.
It contains the basic tools needed to install, tune, and service the base
station.
Base Station
Calibration Test
Unit & Cable
The Base Station Calibration Test Unit supports test and diagnosis. It is
available for order under TBA0STU. It contains a breakout box, tone
source and speaker.
5.6 Mounting the Base Station
1. Fit the base station into the cabinet or rack and secure it firmly with
an M6 (or 0.25in if using the imperial system) screw, flat and spring
washer in each of the four main mounting holes
b, as shown in
Figure 5.3 on page 68.
2. The base station can be wall-mounted by rotating the front mounting
brackets and fitting the optional rear brackets (TBBA03-01). When
the base station is wall-mounted ensure the airflow is from bottom to
top (front panel mounted down) or side to side.
3. For transport or in installations subject to vibration, the base station
should be supported at the rear using a transit bracket
(Tait recommends using the TBBA03-04 transit bracket).