Pump Down Operation SiBE041101
239 Trial Operation and Field Settings
1. Pump Down Operation
Outline In order to protect the environment, be sure to conduct pump down operation when relocating or
disposing the unit.
Detail 1) Remove the valve caps from the liquid stop valve and the gas stop valve.
2) Carry out forced cooling operation.
3) After 5 to 10 minutes, close the liquid stop valve with a hexagonal wrench.
4) After 2 to 3 minutes, close the gas stop valve and stop the forced cooling operation.
Refer to page 240 for forced cooling operation.
Gas stop valve
Valve cap
Close
Liquid stop valve
Service port
(R13628)
Hexagonal
wrench

Table of Contents

Other manuals for Daikin J-Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Daikin J-Series and is the answer not in the manual?

Daikin J-Series Specifications

General IconGeneral
BrandDaikin
ModelJ-Series
CategoryAir Conditioner
LanguageEnglish

Related product manuals