Page 2-2 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400
Revision 1 190-00577-04
wiring harness. Any additional connections, such as pitot/static plumbing, must also be accomplished at
this time.
NOTE
Throughout the next section of this document, many screen shots and examples are used
to illustrate the software and configuration loading process. Although every effort has
been made to ensure accuracy of such examples, changes may occur. Always refer to the
Required Equipment List for the correct software file names, versions and part numbers.
2.5 G1000 Software/Configuration Procedure
The G1000 is not airworthy unless software and configuration are accomplished successfully as described
in these procedures. The following diagram depicts an overview of the software/configuration sequence
for the G1000 system. If any problems are encountered during the loading process, see Section 2.8. It is
extremely important that each LRU software load be completed successfully.
Figure 2-1. Software/Configuration Overview