To delete a CHAP entry
1. In the Configuration View panel, right-click Hosts or a specific host and then select Provisioning >
Configure CHAP. If any CHAP entries exist, a table shows them by node name.
2. Select the entry to delete.
3. Click Delete Entry. If the task succeeds, the entry is removed from the CHAP entries table.
Modifying a schedule
To modify a schedule
1. In the Configuration View panel, right-click the system or a volume or a snapshot and select
Provisioning > Modify Schedule.
2. In the main panel, select the schedule to modify.
3. Set the options:
• Snapshot Prefix. Optionally change the default prefix to identify snapshots created by this task. The
prefix is case sensitive and cannot include a comma, double quote, or backslash. Automatically
created snapshots are named prefix_s001 through prefix_s1023.
• Snapshots to Retain. Select the number of snapshots to retain. When the task runs, the retention
count is compared with the number of existing snapshots:
• If the retention count has not been reached, the snapshot is created.
• If the retention count has been reached, the volume's oldest snapshot is unmapped, reset, and
renamed to the next name in the sequence.
• Start Schedule. Specify a date and a time in the future for the schedule to start running.
• Date must use the format yyyy-mm-dd.
• Time must use the format hh:mm followed by either AM, PM, or 24H (24-hour clock). For
example, 13:00 24H is the same as 1:00 PM.
• Recurrence. Specify how often the task should run. It is not recommended to set the interval to less
than two minutes. The default and minimum interval to replicate a volume is 30 minutes.
• Time Constraint. Specify a time range within which the task should run.
• Date Constraint. Specify days when the task should run.
• End Schedule. Specify when the task should stop running.
4. Click Modify Schedule.
5. Click Yes to continue; otherwise, click No. If you clicked Yes, a processing dialog appears. When
processing is complete a success dialog appears.
6. Click OK.
Deleting schedules
If a component has a scheduled task that you no longer want to occur, you can delete the schedule. When
a component is deleted, its schedules are also deleted.
To delete task schedules
1. In the Configuration View panel, right-click the system or a volume or a snapshot and select
Provisioning > Delete Schedule.
2. In the main panel, select the schedule to remove.
3. Click Delete Schedule. A confirmation dialog appears.
4. Click Yes to continue; otherwise, click No. If you clicked Yes, a processing dialog appears. If the task
succeeds, the schedules are removed from the table and from the Configuration View panel. When
processing is complete a success dialog appears.
5. Click OK.

Table of Contents

Other manuals for HP P2000 G3

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the HP P2000 G3 and is the answer not in the manual?

HP P2000 G3 Specifications

General IconGeneral
BrandHP
ModelP2000 G3
CategoryStorage
LanguageEnglish

Related product manuals