REASSEMBLY
The reassembly procedure is the reverse
of
the disassembly procedure
Caution:
Clean the governor body with compressed air prior to reassembling.
When reassembling the throttle valve shaft, apply
MP
grease thinly to the governor body needle bearing.
After completing the throttle valve shaft and valve reassembly, check for smooth operation.
Temporarily install the air governor spring to the following dimension.
I
Effective spring turns
B
I
11 turns
1
13 turns
I
Adjusting screw protrusion
A
1 ton vehicle
16.8
mm
(0.661 in.)
2 to 3 ton vehicle
21.9
mm
(0.862 in.)
4Y-E Repair
Section 1.1.4

Table of Contents

Other manuals for Toyota 8FGCU30

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Toyota 8FGCU30 and is the answer not in the manual?

Toyota 8FGCU30 Specifications

General IconGeneral
Model8FGCU30
CategoryForklifts
Engine TypeInternal Combustion
Load Capacity6, 000 lbs
Maximum Lift Capacity6, 000 lbs
Tire TypePneumatic
Fuel TypeGasoline/LPG
Power SourceInternal Combustion
Engine ModelToyota 4Y
Mast Type3-stage