7.4 Measuring Demand
● Measuring Demand
In this section, you can set up the start and stop times of integration to measure
a demand value and interval electric energy. From these, you obtain the
maximum demand (power and the date and time of occurrence of it) consumed
during this period.
Checking settings:
To save data in integration measurement, you need to make settings.
(Start and stop times of integration, interval time during which data is saved,
items to be saved, and so on)
Save 1/2 screen: Save 2/2 screen:
SEE ALSO
For more information on settings, see Chapter 6, Configuring Settings, Section 6.4,
Save Data Settings 1/2, and Section 6.5, Save Data Settings 2/2.
Set values can also be checked using the F4 key (SETTING CHECK) on the
Integrate screen. If a set value needs to be changed, press the F1 key (SETUP)
on the Setting Check screen.