Rockwell Automation Publication 1756-UM001M-EN-P - February 2012 163
Develop Applications Chapter 10
Scheduled and Unscheduled Programs
The scheduled programs within a task execute to completion from first to last.
Programs that aren’t attached to any task show up as unscheduled programs.
Unscheduled programs within a task are downloaded to the controller with the
entire project. The controller verifies unscheduled programs but does not execute
them.
You must schedule a program within a task before the controller can scan the
program. To schedule an unscheduled program, use the Program/Phase Schedule
tab of the Task Properties dialog box.
Figure 30 - Scheduling an Unscheduled Program

Table of Contents

Other manuals for Allen-Bradley ControlLogix L7

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Allen-Bradley ControlLogix L7 and is the answer not in the manual?

Allen-Bradley ControlLogix L7 Specifications

General IconGeneral
BrandAllen-Bradley
ModelControlLogix L7
CategoryController
LanguageEnglish

Related product manuals