10
INOVANCE TECHNOLGY EUROPE GmbH
SV660N Startup Procedure_EN_v1.4_20220826.docx
6.4 COMMISIONING AND OPERATION
The following figure shows the general procedure for axis commissioning:
Disable STO.
See 4.1 Connection of STO terminals
Check:
From InoDriverShop: Communications
From EtherCAT: Control & Status word
See 6.6.1 Inertia Auto-tuning
See 6.6.2 STUNE or 6.6.3 ETUNE
See 6.4.2 Factory Default
Axis Not Ready (nr)
Check parameter H0B-63
“Not Ready Status”
Power ON by:
From InoDriverShop: see 6.4.3 Jogging
From EtherCAT Master: ex. MC_Power