Malfunctions during crane operation
14.6 Hydraulic emergency operation
Operating Manual GMK6300L 3 112 xxx en 14 - 69
xx.xx.xxxx
14.6.4 Establishing the hydraulic circuits required
To establish an hydraulic circuit, switch over the required valves and possi-
bly also perform additional switching operations for lifting/lowering or
slewing.
Switching over
valves
The valves 1 to 5 are numbered.
For crane operation
• Switch the valves 1 to 5 downward.
s
G
Danger from mutual interference of the power units!
For crane operation, always switch all the valves 1 to 5 down. This prevents
the power units suddenly starting to move.

Table of Contents

Other manuals for Manitowoc Grove GMK6300L-1

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc Grove GMK6300L-1 and is the answer not in the manual?

Manitowoc Grove GMK6300L-1 Specifications

General IconGeneral
BrandManitowoc
ModelGrove GMK6300L-1
CategoryConstruction Equipment
LanguageEnglish

Related product manuals