3-20 BA DT08 SL EN – Edition 1.0 * * dt08b330.fm
Operation
Crane handling the machine
Safety instructions
The crane and the lifting gear must have suitable dimensions
Crane handling the machine requires suitable lifting gear
Secure the machine against unintentional movement!
Danger!
Incorrect crane handling of the machine –
Danger of accidents!
Ensure that no-one is near the machine!
Have loads fastened and crane operators guided by experienced persons
only! The person guiding the crane operator must be within sight or sound
of him
Ensure that the crane and the lifting gear (cables, chains) have sufficient
load-bearing capacity!
Only raise the machine with an empty loader unit and skip
Stay clear of suspended loads!
It is essential that you read the safety instructions at the beginning of this
chapter and follow any other safety instructions relevant in your country!
Load the machine as follows:
Empty the skip and the loader unit
Lower the skip
Stop the engine
Remove the ignition key.
Use suitable lifting gear, chains etc.
Length L1 of the lifting gear on the skip must be at least 2.0 m long
Length L2 of the lifting gear (two cables or chains) on the control stand must be at
least 2.0 m long
Slowly raise the machine
Fig. 53: Craning operation
L1
L2
L2
L1
L2

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Wacker Neuson DT08-D and is the answer not in the manual?

Wacker Neuson DT08-D Specifications

General IconGeneral
BrandWacker Neuson
ModelDT08-D
CategoryConstruction Equipment
LanguageEnglish

Related product manuals